|
Project History
The development and implementation of a major new transportation corridor such
as this evolves in several distinct phases including planning, project
development & environmental study (PD&E), design, right-of-way
acquisition and construction.
Regional Planning Study
(completed)
description:
The purpose of the study was to determine the need for additional
transportation capacity across the St. Johns River, between Clay and St. Johns
Counties.
The study assessed the travel demand between Clay and St. Johns counties,
both at the present time and in the future. It considered all travel between the
counties, including 'through' trips which pass through both counties.
The study evaluated how traffic would change if new capacity, in the form of
a new bridge across the St. Johns River and approaching roadways, were added at
various test locations. Traffic forecasts were then developed for the new bridge,
existing bridges, and the connections to the existing roadway network.
corridors:
results:
The planning study concluded that travel demand between Clay and St. Johns
counties is expected to increase tremendously in the future due to
population growth and the large scale developments in each county. The study concluded that
additional roadway capacity between Clay and St. Johns counties is needed to
serve future traffic.
public
involvement activities:
2001
| September 12 |
Kickoff Meeting for a Regional
Transportation Study-Connecting Clay and St. Johns County
Switzerland Point Middle School, St. Johns
County
|
| September 13 |
Kickoff Meeting for a Regional
Transportation Study-Connecting Clay and St. Johns County
Robert M. Patterson Elementary, Clay
County
|
2002
|
May
29 |
Alternatives Meeting for a Regional Transportation
Study-Connecting Clay and St. Johns County
Switzerland Point Middle School, St. Johns County
|
|
May
30 |
Alternatives Meeting for a Regional Transportation
Study-Connecting Clay and St. Johns County
Robert M. Patterson Elementary, Clay County
|
Corridor Study (completed)
description:
Following the planning study, the project entered the early stages of the
PD&E study. This particular phase, called the Corridor Study Phase, built
upon the findings identified in the planning study. During the initial phases of
the corridor study, a total of eight corridors were identified and proposed.
Three of the corridors used existing roads wholly or in part to provide the
connection between Blanding Blvd. and Interstate 95/SR 9B. The remaining five
used an entirely new highway location. After establishing the corridor
locations, the effectiveness of each corridor was measured in terms of
satisfying the future transportation need. It was determined that the three
corridors which used the existing road network would not be able to meet the
future highway capacity needs. The remaining five corridors were evaluated for
various impacts that would result including environmental, social and economic
impacts. This evaluation also included the "No Build" alternative,
which was used as a baseline to measure all alternatives against.
corridors:
| Pink |
Brown |
Purple |
Orange |
Green |
results:
After reviewing public comments, along with engineering, environmental and
traffic analysis, the decision was made to carry forward both river crossing
locations and their associated corridors to the Project Development and
Environment (PD&E) Study phase of the project.
The Green and Orange Corridors were dropped from further consideration.
A new corridor, titled the Black Corridor, was added in response to
comments that the Purple Corridor did not connect to I-95 in a southerly direction.
public
involvement activities:
2004
|
March 30 |
Alternatives Meeting for St. Johns River Crossing
Corridor Study
Switzerland Point Middle School, St. Johns County
|
|
April 1 |
Alternatives Meeting for St. Johns River Crossing
Corridor Study
Clay High School, Clay County
|
Conceptual Design & EIS Phase
(Underway)
description:
The purpose of the PD&E study is to evaluate in further detail the impacts
to the social, natural and
physical environment of each alternative. The impacts will be documented in an
Environmental Impact Statement (EIS) for review and approval by the Federal
Highway Administration. The study will be used to support the decisions
concerning if and where the improvements should be built and will determine
whether or not further modifications will need to be made to the proposed
alternatives.
alternatives:
| Purple |
Black |
Pink 1 & 2 |
Brown 1 & 2 |
public
involvement activities:
2005
|
November 1 |
Alternatives Meeting for
the St. Johns River Crossing Project Development & Environment Study
World Golf Village,
St. Johns County
|
|
November 3 |
Alternatives Meeting for
the St. Johns River Crossing Project Development & Environment Study
Clay County
Fairgrounds, Clay County
|
2006
|
August 29 |
Alternatives Meeting for
the St. Johns River Crossing Project Development & Environment Study
St. Johns River
Community College, Clay County
|
|
August 31 |
Alternatives Meeting for
the St. Johns River Crossing Project Development & Environment Study
World Golf Village,
St. Johns County
|
|
September 7 |
Alternatives Meeting for
the St. Johns River Crossing Project Development & Environment Study
Cecil Conference
Center, Duval County
|
Design (Currently not scheduled)
Right-of-Way
Acquisition (Currently not scheduled)
Construction
(Currently not scheduled)
|